Greeneco Energy

Focusing on clean, environmentally friendly and renewable energy that does not harm human health, which is of critical importance for our country, Acarsan Holding invests in the most reliable and sustainable energy sources in the world with Greeneco.

In this context, its activities in the field of geothermal energy are supported by additional investments, and its studies and investments continue in areas such as HEPP, solar and wind energy.

Geothermal

Denizli - Sarayköy - Tekkehamam

The installation of the first power plant of the GREENECO GPP first stage investment, consisting of two units with 26 MWm/25.6 MWe power, was completed and an annual production capacity of 204,800,000 kWh with an installed capacity of 25.6 MWe was reached by the end of 2016.

With the completion of the third and fourth units of the second stage investment of GREENECO GPP with a capacity of 26 MWm/25.6 MWe in 2017-2018, an annual production capacity of 409,600,000 kWh with an installed capacity of 51.2 MWe was reached as of 2018.

The installation of the 28.50 MWm / 28.05 MWe (206,448,000 kWh) power plant of the GREENECO GPP third stage investment was completed in 2019 and an annual production capacity of 616,048,000 kWh with an installed capacity of 79.25 MWe was reached as of the end of 2019.

The installation of the 26.40 MWm / 26.00 MWe (191,360,000 Kwh) power plant of the fourth stage investment of GREENECO GPP was completed in October 2020 and an annual production capacity of 807,408,000 kwh was reached with an installed capacity of 106.90 MWm / 105.25 MWe.

It has been determined that 106.90 MWm/105.25 MWe, i.e. an annual average of 807.408 million kWh of electricity can be generated based on geothermal resources in the Greeneco licence area. An investment of USD 500 million has been reached with the second, third and fourth stage projects that started immediately after the USD 110 million investment completed in 2016.

Greeneco Energy plans to reach a total installed capacity of 200 MWe in its 2,250 hectare area in Denizli - Sarayköy - Tekkehamam region.

Bolu - Seben - Kesenözü

In a geothermal area of 4,200 hectares (42,000 acres) in Bolu - Seben - Kesenözü, temperatures above 96°C have been obtained in the first drilling, and a 5 MW power plant with Organic Rankine Cycle technology is planned to be commissioned in 2022. Both electricity generation and residential heating and greenhouse heating from recycling are planned. This region, located in the middle of Istanbul and Ankara, has an ideal structure for both thermal tourism and nature tourism with its virgin nature. With this investment, it is planned to encourage entrepreneurial tourism companies to health tourism.

Muğla - Köyceğiz - Sultaniye

In the centre of Dalyan, in a uniquely beautiful geothermal area of 5,500 hectares (55,000 acres), one side of which extends to Köyceğiz Bay and the other side to Köyceğiz Lake, it is planned to establish a luxury hotel for modern baleonogy and health tourism. On the other hand, it is planned to work with greenhouses (especially flower greenhouses) on a revenue-sharing basis with the water coming out of the underground and approaching 50°C.

Muğla - Fethiye - Girmeler

In the geothermal area of 4,800 hectares (48,000 acres) located on the Saklıkent road, in a region where history and nature are intertwined; thermal tourism and greenhouse cultivation based on income sharing are planned.

Mersin - Silifke - Keben

In Silifke, the most touristic district of Mersin, 3,500 hectares (35,000 acres) of geothermal area located at the foot of Göksu Canyon is planned to revitalise thermal tourism and nature tourism.

Konya - Karapınar - Üzecik Dağı - Yarımca

In the geothermal area of 4,500 hectares (45,000 acres) located in the Üzecek Mountain area of Karapınar district of Konya, which has different natural and historical beauties, thermal tourism, nature tourism and greenhouse cultivation are planned.

HEPP (HES)

Çatak - Deliktaş Regulator and Hydroelectric Power Plant

It is planned to contribute to the national economy by converting the hydraulic potential energy of Çatak Water between 1,490 and 1,360 metres in Çatak district of Van province into electrical energy.

Project characteristics are as follows:

  • Project Flow (m³/sec): 2x21,25+10=52,50
  • Installed Power (MW) : 2 x 20,030 +9,440-49,50
  • Annual Production (GWh): 157.418

Besik Regulator and Hydroelectric Power Plant

It is planned to convert the hydraulic potential energy between the elevations of 1.756-1.635 metres of Mukus Stream in Bahçesaray district of Van province into electrical energy and contribute to the national economy.

Project characteristics are as follows:

  • Project Flow Rate (m³/sec): 2x10+2,5=22,50
  • Installed Power (MW) : 2 x 10,075 +2,500-22,65
  • Annual Production (GWh): 77.036

Tüğsüs Regulator and Hydroelectric Power Plant

It is planned to convert the hydraulic potential energy between 1.601-1.480 metres elevation of Mukus Stream in Bahçesaray district of Van province into electrical energy and contribute to the national economy. It is immediately following the Beşik HEPP project.

Project characteristics are as follows:

  • Project Flow Rate (m³/sec): 2x13+4-30,00
  • Installed Power (MW) : 2 x 12,75+3,9-29,40
  • Annual Production (GWh): 90.106

Gökay 1 Regulator and Hydroelectric Power Plant

It is planned to convert the hydraulic potential energy between the elevations of 1.345-1.203 metres of Hizan Stream (Akkilise Stream) in the borders of Hizan district of Bitlis province into electrical energy and to participate in the national economy.

Project characteristics are as follows:

  • Project Flow Rate (m³/sec): 2x11,35+4,80-27,50
  • Installed Power (MW) : 2 x 12,85+5,45-31,15
  • Annual Production (GWh): 94.340

Gökay 2 Regulator and Hydroelectric Power Plant

It is planned to convert the hydraulic potential energy between the elevations of 1.200-1.125 metres of the Hizan Stream (Akkilise Stream) in the borders of Hizan district of Bitlis province into electrical energy and contribute to the national economy. Gökay 1 HEPP project is in the immediate continuation of the project.

Project characteristics are as follows:

  • Project Flow Rate (m³/sec): 2x 14,50 +6,00 -35,00
  • Installed Power (MW) : 2x7,97+3,30-19,24
  • Annual Production (GWh): 61.088

SPP (GES)

First Stage 40 MW Combined Renewable Solar Energy Investment

In order to reach an installed capacity of 40 MW SPP, which we have started to invest in the first stage within our Denizli geothermal licence area, the SPP plants to be established on a total area of 600,000 m2 are planned to be commissioned in October 2021.

With the 40 MW facility, it is aimed to generate 65 million to 77 million KW/h of electricity annually depending on the technology used.

The value we add to the national economy and the world ecosystem with the electricity we produce within Greeneco Enerji A.Ş. becomes increasingly important with each passing day. Our efforts to increase the added value, to achieve more efficiency and to increase production continue with all our strength.